The Procurement Monitoring Bureau (the “IUB”) is the Latvian governmental authority which hears disputes about the outcomes of the procurement procedures most frequently and before ever proceeding to court. Losing tenderers are mostly interested in receiving the green light to sign the contract and then a profit-generating contract after that. However, if the IUB rejects the losing tenderer’s appeal and allows the contract to be signed, the contracting authority, having obtained the go-ahead, signs the contract with the winning tenderer even before the losing tenderer has time to file a court application. There are a variety of significantly complex aspects of applying for interim measures that, in general, discourage applicants from continuing to litigate disputes and force them to accept the unsuccessful outcomes of the procurement process.
The authors of this article highlight the specific conditions under which the losing tenderers may be eligible to recover lost profits even if the contracting authority has already signed the contract with another tenderer. This in turn is a crucial consideration when deciding whether to file a lawsuit after having to deal with an improper results evaluation and failing to persuade the IUB.
The essential requirements for receiving unearned profits and filing an appropriate claim are listed below.
Several criteria must be met in order to recover lost profits
Firstly, the losing tenderer can only claim lost profit if, in the absence of the relevant procurement procedure infringement, it should have received the right to enter into the procurement contract and would have been granted such right.[1] Therefore, it is not enough that the outcomes of the relevant procurement disputes are erroneous or illegal. It must be objectively concluded that if the “key error” in the evaluation result had been corrected, the losing tenderer would have won indisputably.
Secondly, only after determining whether the losing tenderer could have objectively won the procurement can the question of whether the losing tenderer would have gained a profit be addressed.[2]
A particular amount of lost profits must be actively and conclusively proven by the losing tenderer when presenting a claim for a recovery of such profits. Proving an exact amount of lost profit is challenging as it cannot be based solely upon assumptions. The reason for how much profit the claimant would have earned must be supported by clear evidence.[3]
The amount of lost profit must be the amount the losing tenderer would have received if the error or breach had not occurred. Justifying the amount of lost profit is a difficult process that necessitates a diligent and detailed assessment.
For example, the court shall not be persuaded by the claimant’s opinion alone, along with the procurement contract and accounting records.
When gathering the required evidence, it is important to bear in mind, the amount of lost profit is mostly determined by using specific calculations.[4]
However, such a calculation can be made taking into account various factors arising from the applicable case-law, for example:
The aforementioned elements are not all-inclusive. A precise determination of the sufficient collection of evidence should be assessed on a case-by-case basis since the court’s practice on this issue continues to evolve.
Conclusions
To summarise, the conditions which must be satisfied when making a claim for lost profit as a losing bidder:
[1] The judgment of the Senate of March 30 2015 in case No SKA-585/2015, Clause 8.
[2] The judgment of the Senate of October 22 2014 in case No SKA-807/2014, Clause 12, 13.
[3] The judgment of the Senate of April 20 2017 in case No SKA-372/2017, Clause 12.
[4] Torgāns K. Saistību tiesības. Otrais papildinātais izdevums. Rīga: Tiesu namu aģentūra, 2018, 206.lpp.
[5] Law on Compensation for Damages Caused by State Administrative Institutions, Article 12, Section 3.
[6] The judgment of the Senate of May 27 2020, case No SKC 309/2020, Clause 11.
[7] The judgment of the Senate of May 10 2022, case No SKA 471/2022, Clause 48.
[8] For more details, see the court's assessment of the mentioned issue in paragraph 15 of the judgment of the Senate of September 22 2017 in case No SKA-558/2017.
VILGERTS team advised AS DelfinGroup on the conditions of the unsecured bond issue prospectus in the amount of EUR 15 million. The prospectus for the issue of unsecured bonds includes both the opportunity for new investors to purchase the new unsecured bonds from 4 August 2023, as well as the opportunity for existing investors of certain categories of bonds to exchange existing bonds for new ones.
August 22, 2023
The VILGERTS’ team is advising East Capital Real Estate on its acquisition of 100% of the shares in Hepsor U30 SIA (a subsidiary of the Estonian company, Hepsor Latvia OÜ), which owns a commercial building called “StokOfiss U30”, developed by Hepsor (with a total rental area of 3,642 m2). The transaction is valued above EUR 5 million. StokOfiss U30 is a multifunctional commercial building with a three-in-one leased space solution, including a sales premises, office space and a warehouse.
June 13, 2023
VILGERTS advised SIA "Biļešu paradīze", a company of Ekspress Grupp AS, in a dispute in which SIA "Biļešu serviss" contested the results of the procurement tender concerning the sale of tickets for the upcoming and the largest national “Song and Dance Festival” in Latvia. As a result, the tender results were left unaltered and SIA "Biļešu paradīze" concluded a contract with the contracting authority.
May 16, 2023
The VILGERTS team advised the owner and manager of Galleria Riga, "East Capital Real Estate", in successfully finalising a significant long-term lease agreement with Workland. The agreement involves a remarkable investment (exceeding EUR 3 million) and aimed at transforming the expansive fifth floor of Galleria Riga, spanning an impressive area of 3,200 m2, into state-of-the-art co-working offices.
May 16, 2023